NEW QUESTION # 164
The question: 'Is the project actually following the processes and procedures as set out in the quality plan?' would be answered by?
- A. Quality alignment.
- B. Quality assurance.
- C. Quality control.
- D. Quality improvement.
Answer: B
NEW QUESTION # 165
A typical risk management process would follow the steps:
- A. assessment, planning, managing. response.
- B. identification, planning, response. closure
- C. identification. analysis, response. closure.
- D. assessment, analysis. closure. response.
Answer: C
NEW QUESTION # 166
Which one of the following does project change control primarily seek to ensure?
- A. Management costs of the project do not increase.
- B. Any decrease in the scoped deliverable of the project is rejected.
- C. No reduction in the perceived quality of the project outcome.
- D. All variance to the project scope is evaluated.
Answer: D
NEW QUESTION # 167
What is the most likely conclusion resulting from a PESTLE analysis?
- A. The agreed end date for the project.
- B. A list of possible stakeholders.
- C. The number of project phases necessary.
Answer: B
Explanation:
D The size of the project team required.
NEW QUESTION # 168
Which statement best describes a responsibility of the project manager:
- A. to delegate all accountability for managing time, cost and quality to team leaders
- B. to deliver the project objectives to enable benefits to be realised.
- C. to be the sole source of expertise for estimating techniques on cost and time.
- D. to take ultimate accountability for the delivery of the business benefits.
Answer: B
NEW QUESTION # 169
In which phase of the project should the Procurement Strategy be written?
- A. Concept
- B. Definition
- C. Transition
- D. Deployment
Answer: B
NEW QUESTION # 170
Which one of the following is the best description of project scope?
- A. Scope is detailed in the business case.
- B. Scope defines what is NOT delivered by the project.
- C. Scope is an outcome of the scheduling and estimating processes.
- D. Scope is the total work content of a project.
Answer: D
NEW QUESTION # 171
What is the key benefit of having configuration management in the project?
- A. It manages the impact of change to the project scope.
- B. It is A. means to justify to the customer variances from the original objectives.
- C. It allows a thorough assessment of the factors that are most likely to affect the change.
- D. It ensures that the delivered product most closely meets the needs of the customer.
Answer: A
NEW QUESTION # 172
On examining a particular risk in the project there is some uncertainty among the project team of how important this risk is to the project. How would you advise the team on how the significance of the risk is to be determined?
- A. By assessing its impact on project objectives,
- B. By assessing its probability of occurrence.
- C. By assessing both its probability of occurrence and its impact on project objectives.
- D. By assessing its effect on the business case.
Answer: C
NEW QUESTION # 173
When managing the internal context, the project manager should especially be aware of:
- A. new legislation.
- B. organisational strategy, policies and frameworks.
- C. competitive positioning.
Answer: B
Explanation:
D business continuity.
NEW QUESTION # 174
What is the term given to the senior management team that set the strategic. direction for a project?
- A. Programme director.
- B. Project steering group.
- C. Change control board.
- D. Project management office.
Answer: A
NEW QUESTION # 175
Which of these is not part of the linear project life cycle?
- A. Concept
- B. Definition
- C. Operations
- D. Transition
Answer: C
NEW QUESTION # 176
Understanding who stakeholders are and their needs is a key duty of
- A. the project manager.
- B. the business sponsor.
- C. the quality manager.
- D. the key users,
Answer: A
NEW QUESTION # 177
The accuracy of an estimate should:
- A. decrease as a project progresses through its lifecycle.
- B. increase as a project progresses through its lifecycle.
- C. vary independently of where the project is in its lifecycle
- D. stay constant throughout the project.
Answer: B
NEW QUESTION # 178
Configuration management is defined as a process which enables:
- A. the identification of differences would affect successful completion of objectives.
- B. the safeguarding of stakeholder benefits, outputs and outcomes to requirements.
- C. the creation, maintenance, controlled change and the quality control of a scope of work.
- D. a structured approach to move an organisation from a current state to a future desired state.
Answer: C
NEW QUESTION # 179
Project success criteria are best defined as:
- A. the activities or elements of the project which are considered to be critical to success
- B. the factors that, when present in the project are most conducive to a successful outcome.
- C. the qualitative or quantitative measures by which the success of the project is judged.
- D. the measures that establish if project activities are ahead or behind schedule.
Answer: C
NEW QUESTION # 180
When the project progresses through the life cycle. which one of the following aspects would be expected to occur?
- A. The accuracy and level Of contingency requirement both increase.
- B. The accuracy of the estimate increases and the level of contingency requirement reduces.
- C. The accuracy and level of contingency requirement both reduce.
- D. The accuracy of the estimate reduces and the level of contingency requirement increases.
Answer: B
NEW QUESTION # 181
......
Latest APM-PFQ Exam Dumps APM Exam: https://exams4sure.pdftorrent.com/APM-PFQ-latest-dumps.html