NACE-CIP1-001 (Coating Inspector Level 1) Exam is a professional certification program designed for individuals who are involved in the field of corrosion protection and coatings. NACE-CIP1-001 exam is administered by the National Association of Corrosion Engineers (NACE) and is considered to be the gold standard in coatings inspection. Coating Inspector Level 1 certification program is designed to provide individuals with the knowledge and skills necessary to perform the duties of a coatings inspector.

 

NEW QUESTION # 12
You are the NACE Inspector on a 5000 sq. ft. job where SSPC PA 2 has been specified.
Assuming all areas are in compliance, how many gauge readings and spot measurements are required?

  • A. 105 Gauge Readings resulting in 35 Spot Measurements
  • B. 225 Gauge Readings resulting in 75 Spot Measurements
  • C. 45 Gauge readings resulting in 15 Spot Measurements
  • D. 75 Gauge Readings resulting in 25 Spot Measurements

Answer: B


NEW QUESTION # 13
If a Thermoset coating is heated it will:

  • A. Soften when heated and retain its softness when cooled
  • B. Soften when heated and return to its original hardness when cooled
  • C. Harden and retain its hardness when cooled
  • D. Harden and return to its original hardness when cooled

Answer: C


NEW QUESTION # 14
An exposed area of the substrate or previous coat of a conductive coating material, often caused by poor application technique is called

  • A. checking.
  • B. cracking.
  • C. sagging.
  • D. holiday.

Answer: D


NEW QUESTION # 15
You are the NACE Inspector on a tank lining project where a 50% solids epoxy tank lining is being applied. After application of the 19 coat you notice small blisters in some areas of the applied lining.
Your FIRST preferred course of action is to:

  • A. Break the blisters to see what's inside
  • B. Document the problem and advise the Contractor and Owner's representative
  • C. Extract any liquid that may be inside the blister and send it to the lab for further analysis
  • D. Document the problem and advise the Contractor

Answer: B


NEW QUESTION # 16
If the project specification DOES NOT state the specific DFT measurement standards, the inspector should use

  • A. NACE 2/SSPC SP10
  • B. a recognized industry standard like SSPC-PA 2 that is broadly accepted
  • C. their best judgment based on similar projects and specifications.
  • D. a detailed checklist and document the lack of a standard.

Answer: B


NEW QUESTION # 17
Non Conformance Reports are completed by the Inspector:

  • A. In every instance that an item does not meet the specification requirements
  • B. In accordance with the specification's definition of a non-conformance
  • C. When the Inspector and Contractor deem it to be a significant non-conforming item
  • D. When the Inspector deems it to be a significant non-conforming item

Answer: C


NEW QUESTION # 18
ASTM Standards are applicable:

  • A. In Asia
  • B. In the USA
  • C. When specified
  • D. In North America

Answer: C


NEW QUESTION # 19
NACE SP 0178 is a standard for:

  • A. Structural steel to be coated for Atmospheric Service
  • B. Tanks and Vessels to, be Lined for Immersion Service
  • C. Tanks and Vessels to be Externally Coated
  • D. Stainless steel pipe to be Externally Coated

Answer: B


NEW QUESTION # 20
ISO SA 3 is directly equivalent to:

  • A. NACE No. 3/SSPC SP 6
  • B. NACE No. 1/SSPC SP 5
  • C. NACE No. 2/SSPC SP 10
  • D. None of the above

Answer: D


NEW QUESTION # 21
You are the NACE Inspector on a job where the Owner's specification requites you to perform a twice daily check of blast pressure at the nozzle. It is now day 30 on the job and all of your readings have been within compliance. The Contractor complains that these checks taking up much time and in view of the compliant results they are unnecessary.
Your FIRST preferred course of action is to:

  • A. Skip the checks and just record the same readings as you have been getting
  • B. Keep doing the checks and consult the Owner's representative for direction
  • C. Keep doing the checks regardless
  • D. Skip the checks as you are. confident the blast pressure is OK

Answer: B


NEW QUESTION # 22
Solvents are added to coating formulations to

  • A. increase film permeability.
  • B. dissolve binders and form liquid coatings.
  • C. provide color.
  • D. decrease film permeability.

Answer: B


NEW QUESTION # 23
Fine cracks in the surface of a coating that rarely reach the substrate are called

  • A. blistering.
  • B. alligatoring.
  • C. cracking.
  • D. checking.

Answer: D


NEW QUESTION # 24
Common errors that can produce inaccurate readings when using Wet Film Thickness (WFT) gauges include:
Select All That Apply

  • A. Placing the gauge along the longitudinal axis
  • B. Dragging a gauge through wet coating
  • C. Using a damaged gauge

Answer: B,C


NEW QUESTION # 25
You have just received your NACE CIP Level 1 certification when you are asked to supervise a team of uncertified field pipeline inspectors.
Your FIRST preferred course of action is to:

  • A. Advise the prospective employer that you cannot accept the position
  • B. Review the NACE Attestation prior to making a decision
  • C. Meet with the prospective employer to determine the scope of your role
  • D. Accept the assignment without hesitation

Answer: C


NEW QUESTION # 26
Prior to using Inspection Tools the inspector must:

  • A. a), b) & c)
  • B. Read the manufactures' instructions
  • C. Ensure the instrument is within calibration parameters
  • D. Be trained on how to use the instrument

Answer: A


NEW QUESTION # 27
Which of these tests uses a syringe?

  • A. Sleeve test
  • B. Potassium ferricyanide
  • C. Bresle patch
  • D. Soluble salts meter

Answer: C


NEW QUESTION # 28
Safety Data Sheets must be carefully reviewed by:

  • A. The Inspection personnel
  • B. The Owner's personnel
  • C. The Application personnel
  • D. All personnel involved in the job

Answer: D


NEW QUESTION # 29
If the specifier does not identify a restriction level in accordance with SSPC PA 2, the default restriction level is:

  • A. Level 3
  • B. Level 2
  • C. Level 1
  • D. Level 4

Answer: A


NEW QUESTION # 30
When holiday testing is required the Inspector is always required to enforce NACE SP 0188:

  • A. False
  • B. True

Answer: B


NEW QUESTION # 31
What is used to determine compressed air cleanliness?

  • A. Blotter test
  • B. Psychrometer
  • C. Needle pressure gauge
  • D. Profilometer

Answer: D


NEW QUESTION # 32
......